WATERLINE UPDATE SCHEDULE
Completed 2023-2024
* Mabry and Van Sant (Canal City Subdivision)
* N Tinkle Ln
Completed 2024
* Moms Rd
* Diamond Rd
* N Crystal Beach Rd, Island Blvd and Rainbow Blvd
Completed 2025
* N Monkhouse Dr and Resort Rd
* Johnson Crawford Cir, Butterfly Ln, Salt Cedar Ln and Magnolia Ln
* S Boyt Rd, Ocean Breeze Dr, Ocean Sand Dr, Jewel Dr, N. Mae Cir, Bud Dr, S. Mae Cir, Verdia Dr, Ocean View Dr and Ocean Shores Dr
* Beaumont Dr (in Crystal Beach)
Under Construction (August 2026)
* N Boyt Rd, Albermarle, Chadwick, Raleigh, N Yacht Basin Rd, Tangley, Woodway Dr and Boyt Rd W (Kona Kai / Sievers Cove Subdivision)
* Kingston Beach Rd, Martinique Ln, Trinidad Ln and Bahama Ln (Kingston Beach Subdivision)
* S Jacks Rd, S Tinkle Ln and Alma Rd
* Paisley St (Canal City Subdivision)
* Waco Rd (Gilchrist)
Contract 5 to begin Construction in 2027
* South Honeysuckle
* Trinidad (Sandpiper Subdivision)
* Driftwood (Tidelands Subdivision)
* Whitecap (Holiday Beach Subdivision)
* Sea Spray Dr, Cloon St, Buell, Main St, Gulf Rd (Cloon 2 Subdivision)
* Holiday Dr, Surfview Dr (Emerald Beach Subdivision)
* Alberdie Dr
* Kahla Dr
* Yacht Basin, Garth, Tyrell
High Island Grant Project to Begin Construction 2027
* East Mexico Rd, Revia St, Peyton Ln, High School Rd and 5th St
Rollover Pass Water Main Upgrade Grant Project Projected 2028